Day 47: Concrete, Power, and Metal Buildings: The Construction Sprint Begins

Day 47: Concrete, Power, and Metal Buildings: The Construction Sprint Begins

Day 47: Concrete, Power, and Metal Buildings: The Construction Sprint Begins

Yev Galper
Published on: 11/08/2025

170 yards of concrete, power trenches, retaining walls, and the BIG moment—our metal building arrives Aug 14th! Construction is flying now. Fingers crossed!

Pickleball and Padel Club Construction
Day 36: Concrete, Boulders, and Power Lines: When Construction Finally Gets Real

Day 36: Concrete, Boulders, and Power Lines: When Construction Finally Gets Real

Day 36: Concrete, Boulders, and Power Lines: When Construction Finally Gets Real

Yev Galper
Published on: 31/07/2025

We finally poured concrete! 140 cubic yards in 95-degree heat, courtesy of a 147-foot concrete pump beast. Plus: boulder mysteries continue and our metal building arrives Aug 14th. 🚧

Pickleball and Padel Club Construction
Day #28: Construction Reality Check: When Perfect Storms Hit the Build Site

Day #28: Construction Reality Check: When Perfect Storms Hit the Build Site

Day #28: Construction Reality Check: When Perfect Storms Hit the Build Site

Yev Galper
Published on: 25/07/2025

Construction reality: boulders, team miscommunication, a motorcycle accident, and no concrete pumps available. How a perfect storm created a 10-day delay but we're still on track for our big deadline.

Pickleball and Padel Club Construction
Day #23: Big Moves and Bigger Challenges

Day #23: Big Moves and Bigger Challenges

Day #23: Big Moves and Bigger Challenges

Yev Galper
Published on: 19/07/2025

Foundation pour starts Monday! But first, we had to solve a 300-foot retaining wall puzzle involving sediment fences, boulder walls, and a very helpful phone call to Roy.

Pickleball and Padel Club Construction